CDF contractors bank on timely release of funds

Contractors implementing Constituency Development Fund (CDF) projects in Lilongwe have received about 20 percent of their contract sums as initial payments, raising the stakes for timely release of subsequent funds to meet completion deadlines.

The contractors say they have started construction, with some using their own resources to keep the projects moving, but are now relying on further disbursements to sustain the work.

Phiri: We are making payments in phases. | Esnart Tembo

The development comes as government rolls out the reformed CDF programme, which increased the allocation to each constituency from K220 million to K5 billion in the 2026/27 financial year.

Minister of Local Government and Rural Development Ben Phiri said government was releasing funds in phases, based on project progress and contractors’ claims, rather than disbursing the entire allocation.

He said this on Wednesday during a tour of CDF-funded projects in Likuni, Lilongwe Mpenu, Lilongwe Msozi and Chiwamba constituencies to assess their progress.

Bridge constructed under CDF. | Nation

At Sanjiko Health Centre in Lilongwe Mpenu Constituency, Mercury Construction is implementing a K2.8 billion project runs from September 2026 to March 2027.

The company’s contractor Samuel Manguluti said they had received about K500 million but had also invested their own resources to speed up construction.

He said: “We wanted to make sure that the project progresses at a faster pace, so we decided to use some of our own resources in addition to the money we received. 

“However, we have now exhausted those resources and are waiting for further payments after submitting our claims.”

At Malili Health Centre in Likuni Constituency, contractor Anati Jere is constructing a maternity wing, staff houses and a laboratory under a K2.2 billion project running from November 2026 to April 2027. 

The contractor has received K400 million as an initial payment.

At Nanjiri Health Centre in Lilongwe Msozi Constituency, contractor Achobwe is implementing a K1.8 billion project after receiving K300 million, while a K1.2 billion project to construct staff houses at Luwera Health Centre in Chiwamba Constituency has also received an initial 20 percent payment. 

The Luwera project is expected to run from October 2026 to March 2027.

Phiri said the phased funding model was intended to link disbursements to actual implementation and ensure accountability in the use of public resources.

“Government is not releasing the K5 billion to every constituency at once. We are making payments in phases, depending on the progress of the projects, so that contractors can continue working as funds are made available,” he said.

However, the minister said he could not provide a consolidated figure for the amount disbursed nationally, stating councils were managing projects and payments separately.

He said most projects were still at initial stages, with contractors receiving advance payments to begin construction before qualifying for further disbursements.

On security bonds required for the projects, Phiri said contractors were expected to arrange with banks, although some had been allowed to start work while finalising the requirement.

He said the monitoring exercise was intended to establish whether contractors were making progress within agreed implementation periods.

At the four sites, project signboards displayed contract sums and implementation timelines, while community-led groups had been established to monitor construction and follow up on implementation.

Senior Chief Chadza welcomed the construction of Sanjiko Health Centre, saying residents previously travelled long distances to access healthcare.

“Once completed, this health centre will bring healthcare services closer to the people and make it easier for them to access medical attention,” he said.

In July 2026, the Ministry of Finance, Economic Planning and Decentralisation announced the release of about K7.8 billion to councils for preparatory activities, including project identification, technical assessments and procurement.

In September 2026, government announced the release of K85.5 billion to 30 of the country’s 36 councils as advance payments to contractors implementing CDF projects.

Lilongwe District Council subsequently announced on October 19, 2026 that it had handed over 44 projects to contractors for implementation during the 2026/27 financial year. The projects cover health, education, security and community infrastructure.

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Back to top button